Construction Updates

Photo of the Week, Dec 6, 2023

Photo of the week

This is your one-stop-shop for news and information about the construction updates for the new Cowichan District Hospital.

Learn more about the Cowichan District Hospital Replacement project.
Visit the Photo of the Week Archive.

Updates

November 1, 2023: The last two slabs-on-grade for the Inpatient Unit (IPU) and Diagnostic & Treatment (D&T) will be completed this month. The first section of offsite civil work – storm and sanitary sewers, water line infrastructure – on Drinkwater Road is complete. Crews are also working on underground mechanical and electrical, and steel work for the Service Centre.

The team completed the first concrete slab pour for Level 1 of the IPU on October 30 and the remainder of Level 1 will be completed this month. Meanwhile, over at the D&T, the teams will be pouring the first slab for Level 3 this month.

October 4, 2023: At the new CDH, site crews building the future hospital honoured National Day for Truth and Reconciliation by wearing orange shirts, participating in Reconciliation events and raising awareness. Site crews and sub-trades also helped raise an orange shirt and red dress above the site on Saturday, in collaboration with community members and colleagues whose loved ones survived residential school.

September 20, 2023: Construction milestones for September included four more suspended slab* pours slated for the month, including levels 1 and 2 of the Diagnostic & Treatment Centre. The Inpatient Unit slab on grade* construction is underway and suspended slab formwork continues. Programs reviewing their spaces in preparation for the interior work continue to attend mock-up sessions at both CDH and new build site. By the end of September, we anticipate all foundations and the majority of slab on grade pours will be complete for the Diagnostic & Treatment Centre, Inpatient Unit, Lobby and Service Building.

*Glossary of construction terms: 
Suspended slabs are "structural slabs" of concrete that have an occupied floor below them. 
Slab on grade refers to a concrete slab poured on gravel, "at grade".

September 5, 2023: As part of the Project, new storm sewers, sanitary sewers and water lines will be installed on Drinkwater, Bell McKinnon and Herd roads. Work will begin this fall and is expected to occur in phases. See detailed information for local residents, businesses and people travelling through the work areas of the future Cowichan District Hospital: 1) Offsite civil work; 2) Sanitary sewer installation

August 30, 2023: Construction teams are making amazing strides at the site on Bell McKinnon Road. We’ve started to come up and out of the ground as the crews work on the “slab on grade” portion of the Diagnostic & Treatment Centre. Check out our summer update to catch up on the progress to date and meet some of the people who share a passion for creating a new hospital that works for patients, staff and the environment. For those interested in a virtual tour of the new hospital, check out our flythrough video!

May 26, 2023: It’s springtime and construction on the new Cowichan District Hospital is in full bloom! Watch this short video and learn about the Nutsa’maat Alliance, the integrated team delivering this exciting project. See what the site crew has been up to so far in 2023 and find out how you can join the construction or healthcare teams who are working to build a community of care in a community that cares. 

May 2, 2023: The Cowichan District Hospital Replacement Project team finished the largest concrete pour for the new hospital! With three 52-metre-tall concrete pumps and an average of 19 concrete trucks arriving at site per hour from 5 a.m. until 6:30 p.m., 30 workers unloaded an impressive 2,220 cubic metres of concrete!

This remarkable team even completed the pour five hours ahead of schedule. That's amazing! Thank you to everyone who contributed to this milestone and to the neighbours of North Cowichan for their patience as we completed this important work.

concrete_pour.png

April 2023: Construction noise notice

The new Cowichan District Hospital construction project will see an increase in activity over the next few weeks. This includes a long day concrete pour planned for April 21 between 5 a.m. and midnight. Nearby residents and area road users will notice an increase in trucks and noise.

Council for the Municipality of North Cowichan has directed that staff use their discretion to enforce noise infractions and to allow for construction to proceed outside of the regular construction hours, when necessary, until the project is completed.

Bell McKinnon Road will remain open, but intermittent traffic delays may occur as concrete trucks access the site. Please follow all traffic signage and construction personnel directives.

Questions can be directed to newcdh@islandhealth.ca